UPDATES FOR LATEST CONSTRUCTION

JANUARY UPDATE

The first phase of construction kicked-off for LFMP II and Parking Garage C in May 2015, and will conclude in late 2015. In this phase, construction crews have been busy relocating utilities and Department of Aviation offices. Construction of the new cell lot and fountain will also be finished during this phase, as well as the installation of the parking guidance system. The beginning footprint of Parking Garage C can also be seen at this time.